Planning and design
Lower Crow Dam Safety Upgrade
Outlet works and embankment stability upgrades for a dam built in 1922, following the completed spillway work.
- Timeline
- In preliminary design
- Program
- Safety of Dams
- Location
- Lower Crow Reservoir
Project overview
Lower Crow Dam Safety Upgrades consist of upgrades to the spillway, outlet works, and embankment stability during a probable maximum flood, all to address issues of the aging infrastructure (built in 1922). The spillway upgrades were complete over two phase between 2019 and 2022. The outlet works upgrades are in preliminary design that includes two alternatives: Rehabilitation of existing structure, or entirely new structure. The embankment stability upgrades are in preliminary design, which includes a compacted earthen fill with subsurface perforated drain pipe system located along the downstream base of the dam. Environmental mitigation measures are expected due to construction.